Clovelly Hub 6 Month Capacity Outlook

July 1, 2017

LOOP tracks the amount of capacity in service at the Clovelly Hub monthly.  A six month capacity forecast follows in the table below.
 
LOOP performs rigorous maintenance, inspection and testing of its facilities, including its above ground tankage and underground caverns.  At specified intervals, these activities require LOOP to remove assets from active service, thus reducing capacity. Those maintenance and construction activities are just a fraction of the work performed, within the LOOP Safety Management System framework, to continually improve the operation.          
 
LOOP Clovelly Hub 6 Month Capacity Outlook
2017 Total Above Ground Capacity Underground Capacity
July 99% 95% 100%
August 99% 95% 100%
September 88% 95% 87%
October 88% 95% 87%
November 88% 95% 87%
December 88% 95% 87%